31.05.18

Construction Update May 2018

STAGE EIGHT This stage has now been registered. STAGE TEN Construction is complete and compliances are being sought from the authorities. We are on track for lodgement at the Titles Office in June 2018. STAGE ELEVEN Sewer works, drainage, kerb, electrical and communications installation are complete. Footpath is underway and asphalt is scheduled to occur at the end of May. Construction is on track for lodgement at the Titles Office June 2018. STAGE TWELVE Preliminary Earthwork, Sewer works, Drainage and Road Boxing has commenced. Installation of the watermain, kerb and road base is scheduled to occur in June. Construction is on track for lodgement at the Titles Office in August 2018. STAGE THIRTEEN Preliminary Earthwork are scheduled to commence in May, and construction completion is anticipated to occur in October 2018.