STAGE EIGHT
This stage has now been registered.
STAGE TEN
Has been lodged at the Titles Office.
STAGE ELEVEN
Construction is complete and compliances are being sought from the authorities. We are on track for lodgement at the Titles Office in June 2018 with Titles anticipated in July 2018.
STAGE TWELVE
Bulk earthwork, internal sewer works, drainage and road boxing are completed. Installation of the watermain, kerb and road based has commenced. Construction is on track for lodgement at the Titles Office in August, with Titles anticipated in September 2018.
STAGE THIRTEEN
Preliminary earthwork are underway, construction completion is anticipated to occur in October 2018, with Titles anticipated in November 2018.
STAGE FOURTEEN
Civil construction is scheduled to commence in July, with completion anticipated to occur in November 2018, with Titles anticipated in December 2018.