24.07.18
Construction Update July 2018
Rain, hail or shine, the BPG Civil crew continue to build you growing Meridian Community.
STAGE TEN
This stage has now been registered.
STAGE ELEVEN
This stage has now been registered.
STAGE TWELVE
Installation of the watermain, kerb and road base is underway. Electrical and communication installation is occurring in July. Construction is on track for lodgement at the Titles Office in August, with Titles anticipated in September 2018.
STAGE THIRTEEN
Bulk Earthwork, internal sewer works, drainage and road boxing are underway. Installation of the watermain, will commence in July. Construction completion is anticipated to occur in October 2018, with Titles anticipated in November 2018.
STAGE FOURTEEN
Bulk earthworks are underway and sewer works will commence in July. Completion is anticipated to occur in November 2018, with Titles anticipated in December 2018.