WITH WINTER MAKING ITS PRESENCE FELT, OUR CONSTRUCTION TEAM HAVE BEEN MAKING SOME GREAT PROGRESS AT MERIDIAN. READ ON FOR AN UPDATE ABOUT YOUR GROWING COMMUNITY. STAGES TWELVE AND THIRTEEN These stages are now Titled. The streetscape landscaping has now been completed. STAGES FOURTEEN AND FIFTEEN These stages are now Titled. The streetscape tender has been awarded and works will commence in August 2019. STAGE SIXTEEN Bulk earthworks, sewer, drainage and road boxing are now complete, and installation of the water-main has commenced. Kerb, electrical and communications installation will commence in August, followed by footpath and asphalt in September. Construction completion is anticipated to occur in September 2019, with Titles anticipated in September 2019. TITLE FORECAST