Stage 1 & 2
Titles have issued for these stages and we are currently undertaking landscaping of the streetscapes and the entry reserves.
Stages 3 & 4
Construction is complete and compliances have been issued by all the authorities. We are on track for Titles to issue in August 2017
Stage 5
Bulk earthworks, road boxing and sewer works are complete. Water installation and kerb is scheduled to occur in August. Construction is on track for lodgement at the Titles Office in November 2017
Stage 6
Sewer works, drainage, kerb, electrical and communications installation are complete. Footpath is underway and asphalt is scheduled to occur in August. Construction is on track for lodgement at the Titles Office in September 2017
Stage 7
Bulk earthworks and road boxing are nearing completion and sewer construction is underway. Construction is on track for lodgement at the Titles Office in the 1st Quarter of 2018